28 October 2026
5,500 m² production hall for the pharmaceutical industry completed in just three weeks
When pharmaceutical production needs to get up and running quickly, the building must also meet the highest standards right from the start.
During the COVID-19 pandemic, Thermo Fisher Scientific invested around 40 million euros in a new production facility in Lithuania, creating nearly 150 new jobs. The 5,500 m² production hall had to meet the highest hygienic and technical standards, be GMP-compliant and facilitate the integration of cleanroom technology, precise climate control, laboratory areas and sensitive production processes.
Time was a crucial factor. The entire facility was completed in less than four months. At the same time, the hall had to be designed, manufactured and assembled within a matter of weeks – with controlled air quality, stable indoor climate conditions and flexible process areas.
The solution was a bespoke steel hall featuring modular components. Astron designed, manufactured and delivered the steel structure in just three weeks. Prefabricated components and an efficient steel construction method enabled rapid implementation and supported the tight construction schedule.
The building was designed to meet the specific requirements of pharmaceutical production. The energy-efficient LMR600 roof system, high-performance wall elements and high-quality insulation contribute to stable indoor conditions and a controlled working environment. The modular load-bearing structure also allows for future modifications, extensions or the integration of further production and laboratory areas.
The result is a rapidly constructed, flexible and high-performance production hall that meets stringent requirements for hygiene, climate control and process reliability, whilst also being prepared for future demands.
5,500 m². Three weeks for the steel structure. Less than four months for the entire project. A solution that combines speed, technical performance and long-term flexibility.